LATP AirLift โ€” Liquid Hydrogen
Supply Chain for Regional Aviation

Ideathon 2025: Hydrogen Horizons โ€” Monash Energy Club ร— Latrobe City Council. Designed a commercially-viable, three-phase liquid hydrogen supply chain for Latrobe Regional Airport scaling from 2 to 8 hydrogen aircraft. Won the Vestas Award for Best Technical Solution from a competitive field of teams.

Event

Ideathon 2025 โ€” Hydrogen Horizons

Organised By

Monash Energy Club & Latrobe City Council

Award

๐Ÿ† Vestas Award โ€” Best Technical Solution

The Challenge

Latrobe Regional Airport (LATP) is launching zero-emission hydrogen flights to Melbourne. The airport starts with 2 hydrogen aircraft in Year 1, scaling to 8 by Year 3. Each aircraft requires 70 kg of liquid hydrogen per day (two round trips). Teams were asked to answer one question:

โœˆ๏ธ

"How can we develop a commercially-viable supply chain to provide liquid hydrogen to a regional airport?"

Demand grows from 51,100 kg/yr (Year 1) to 204,400 kg/yr (Year 3). The solution must be technically sound, financially modelled, and scalable โ€” judges scored on both dimensions simultaneously.

Our Solution โ€” LATP AirLift

The team โ€” Purnanand Mule (Mechanical), Roopak Watkar (Civil), Athira Thekkethil (Materials), and myself (Materials) โ€” designed a three-phase hydrogen supply chain that begins with pragmatic near-term sourcing and transitions to full on-site green hydrogen generation by Year 3, with a 10-year vision for LATP becoming a regional hydrogen hub.

Phase 1 โ€” 2025
Bootstrap Supply
  • Source LHโ‚‚ from Latrobe H facility (brown coal) or BOC methane Hโ‚‚ plant at Altona
  • Set up small electrolysis plant at airport for future transition
  • Cryogenic truck delivery โ€” 14 trips/year, 20 km haul
  • 1 ร— 3,000 kg cryogenic storage tank on-site
  • 2 refrigeration units for liquefaction
โ†’
Phase 2 โ€” 2026
On-Site Electrolysis
  • Full electrolysis Hโ‚‚ plant operating at airport
  • Desalinated water supply contracted
  • Buy grid green electricity โ€” operate during peak solar hours
  • 2 fridge units + 1 container unit
  • Begin selling surplus Hโ‚‚ and Oโ‚‚ byproduct
โ†’
Phase 3 โ€” 2027
Solar-Powered Hub
  • On-site solar farm commissioned โ€” 100% renewable Hโ‚‚
  • 2 ร— 3,000 kg storage tanks for full fleet demand
  • Continued surplus Hโ‚‚ and Oโ‚‚ revenue stream
  • Foundation for regional hydrogen hub and export
  • 10-year vision: 20 aircraft, battery storage, pipeline

Capital & Operating Cost Model

Every design decision was costed. The full capital and operating expenditure model was developed for the three-phase infrastructure build-out, with revenue projections from Year 2 onwards through surplus hydrogen and oxygen sales.

Infrastructure Component CAPEX (AUD) OPEX/yr (AUD)
2 ร— Small Electrolysis Plants (Phase 1) $240,000$122,640
Cryogenic Transport Truck $1,000,000$10,000
Cryogenic Storage Unit (3,000 kg) $350,000$43,800
Large Electrolysis Plant (Phase 2/3) $10,000,000$2,555,000
Solar PV Farm (Phase 3) $5,400,000$63,000
Total AUD $16,990,000AUD $2,794,440

Revenue Projection โ€” Surplus Hโ‚‚ & Oโ‚‚ Sales

Year Hโ‚‚ Required (kg) Surplus Hโ‚‚ (kg) Revenue from Hโ‚‚ Revenue from Oโ‚‚
Year 1 โ€” 202551,1000$0$73,584
Year 2 โ€” 2026102,20090,958$2,728,740$1,545,264
Year 3 โ€” 2027204,400172,718$5,181,540$3,016,944

How the Revenue Model Was Built

The $9.7M Year 3 revenue figure is not a round estimate โ€” it is a bottom-up calculation from Hโ‚‚ surplus volume and market pricing. The methodology was transparent enough that judges could interrogate any line item.

01
Hโ‚‚ Demand Sizing

8 aircraft ร— 70 kg/day ร— 365 days = 204,400 kg/yr total Hโ‚‚ demand at full Year 3 fleet. Year 1 starts at 2 aircraft (51,100 kg/yr), doubling each year with fleet scaling.

02
Production Capacity & Surplus

The Phase 2/3 large electrolysis plant is sized for 377,118 kg/yr total production โ€” above fleet demand to enable commercial Hโ‚‚ and Oโ‚‚ sales. Year 3 surplus: 377,118 โˆ’ 204,400 = 172,718 kg Hโ‚‚ available for sale.

03
Hโ‚‚ Revenue Calculation

172,718 kg surplus ร— AUD $30/kg (wholesale industrial green Hโ‚‚ price, ARENA 2024 reference) = AUD $5,181,540. Price benchmarked conservatively against current Australian PEM electrolyser output pricing.

04
Oโ‚‚ Byproduct Revenue

PEM electrolysis produces 8 kg Oโ‚‚ per kg Hโ‚‚. 172,718 kg Hโ‚‚ ร— 8 = 1,381,744 kg Oโ‚‚. Priced at AUD $2.18/kg (medical/industrial Oโ‚‚ market, BOC Australia reference) = AUD $3,016,944. Combined Year 3 total: AUD $9,198,484 (~$9.7M including Year 1 Oโ‚‚).

Design Constraints & Key Decisions

The ideathon brief was deliberately constrained: the solution had to work from Year 1 with existing infrastructure, scale to 8 aircraft by Year 3, and be financially defensible โ€” judges assessed commercial viability and technical rigour simultaneously. Three decisions shaped the design:

Strategic Value Proposition

Sustainability Alignment

Aligns with UN SDGs 7, 9, 11, and 13. Supports Australia's 2035 net-zero target. Avoids more than 15,000 tonnes of COโ‚‚ by 2035 across the fleet lifecycle.

Research & Innovation

R&D partnership pathway with Monash University covering microgrids, smart refuelling systems, and AI-optimised logistics for hydrogen delivery scheduling.

Government Funding Eligibility

Eligible for ARENA, CEFC, and Hydrogen Hubs programmes. Directly aligned with Victoria's Hydrogen Roadmap โ€” unlocking public-private co-investment from Phase 1.

Community & Economic Impact

Creates local clean energy jobs in the Latrobe Valley. Repurposes existing coal infrastructure for hydrogen production โ€” a just transition narrative with strong regional stakeholder appeal.

Award & Event

Vestas Award certificate for Best Technical Solution โ€” Ideathon 2025: Hydrogen Horizons, awarded to Jayaraghul Thangaraj Kannan by Monash Energy Club and Latrobe City Council, signed by Madeleine Neaves (President) and Mentor
Vestas Award โ€” Best Technical Solution, Ideathon 2025: Hydrogen Horizons
Winning team holding Vestas Award certificates at Ideathon 2025 โ€” five people standing next to Monash Energy Club banner at Monash University venue, Feedback Form displayed on large screen behind
Team LATP AirLift with Vestas Award certificates โ€” Ideathon 2025 event, Monash University

Outcomes

๐Ÿ† Vestas Award Won

Awarded Best Technical Solution from a competitive field โ€” judged on simultaneous technical rigour and commercial viability.

Full Supply Chain Designed

Three-phase LHโ‚‚ supply chain from bootstrap sourcing through to on-site solar-powered electrolysis, costed at AUD $16.99M total CAPEX.

Revenue Model Demonstrated

Surplus Hโ‚‚ and Oโ‚‚ byproduct sales generate ~AUD $2.8M in Year 2, growing to ~AUD $9.7M by Year 3 โ€” turning infrastructure cost into a commercial asset.

Industry Pitch Delivered

Presented a concise, high-impact technical and commercial case to senior judges from Vestas, Latrobe City Council, and the energy sector.

Tools & Methods

Liquid Hydrogen Supply Chain Cryogenic Storage Design PEM Electrolysis Solar PV Integration CAPEX / OPEX Modelling Revenue Forecasting Phased Infrastructure Rollout Government Incentive Mapping SDG Alignment Technical Pitching Stakeholder Communication