Feasibility Study · TCO Analysis · Green Hydrogen · PEM Electrolysis

Hydrogen Fuel Cell
Forklift Fleet — Feasibility

Technical and economic feasibility assessment for deploying a hydrogen-powered forklift fleet at a large-scale Australian manufacturing facility — covering technology comparison, 10-year TCO modelling, on-site green hydrogen production strategy, and government incentive mapping.

Course

MTE5884 — Engineering Project Evaluation

Institution

Monash University, Clayton

Outcome

Positive Feasibility — Hydrogen Recommended

Project Overview

KMC, a large-scale manufacturing company, operates a forklift fleet that relies heavily on internal combustion engine (ICE) vehicles — producing significant greenhouse gas emissions and creating air quality issues in enclosed logistics spaces. This project evaluated whether a transition to hydrogen fuel cell forklifts was technically sound, economically viable, and strategically aligned with KMC's sustainability objectives.

The assessment benchmarked three competing technologies — ICE, battery-electric (BEV), and hydrogen fuel cell — across emissions, operational performance, infrastructure requirements, and 10-year total cost of ownership. The recommended solution was the Toyota 2.5-ton hydrogen fuel cell forklift, supported by an on-site green hydrogen generation system powered by a 640 kW solar PV array and a 2 MWh battery energy storage system (BESS).

My Contributions

This was a four-person team. Beyond my formally assigned sections, I contributed inputs, edits, and quality review across the whole report — checking the technical accuracy of sections I hadn't drafted and raising the standard of the final submission collectively.

My formally assigned work covered the technically demanding and commercially consequential sections of the report:

Technology Comparison — ICE vs BEV vs Hydrogen

The core analytical challenge was not simply whether hydrogen was better than ICE — it was whether it was the right choice for KMC's specific operational context: multi-shift operations, cold storage environments, high-throughput logistics, and a greenfield facility with no existing infrastructure commitments.

ICE (Diesel/LPG)

  • 42.9 t CO₂/year per unit
  • 75.2 kg NOₓ + 3.2 kg PM/year
  • High fuel cost volatility
  • Not suitable for indoor/cold storage
  • Lowest upfront cost

Not viable — emissions & indoor restrictions

Battery-Electric (BEV)

  • Zero on-site emissions
  • 4–8 hr charge time per shift
  • Performance degrades in cold storage
  • Requires spare battery infrastructure
  • Not suitable for multi-shift without swap

Partial fit — unsuitable for multi-shift/cold

Hydrogen Fuel Cell

  • Zero on-site emissions (water only)
  • ~3 min refuelling, full shift every time
  • Consistent power — no charge degradation
  • Cold-start capable (advances 2014–2024)
  • Higher upfront cost, strong TCO case

Recommended — best fit for KMC's profile

Toyota 2.5-ton hydrogen fuel cell forklift — blue industrial forklift with FUEL CELL branding and Toyota logo Toyota 2.5-ton hydrogen fuel cell forklift — the recommended unit for KMC's fleet

10-Year TCO Model — Fleet of 10

The total cost of ownership model covers a fleet of 10 Toyota 2.5-ton hydrogen fuel cell forklifts operating 2,000 hours per year. The model accounts for capital expenditure, green hydrogen fuel cost, annual maintenance, shared refuelling infrastructure, and residual value at the end of the 10-year period.

AUD $1.05M Capital — 10 Units

AUD $105,000 per Toyota 2.5-ton hydrogen fuel cell forklift

AUD $1.2M Shared Refuelling Infrastructure

On-site hydrogen refuelling station, shared across the fleet

AUD $12/kg Green Hydrogen Fuel Cost

Green H₂ at AUD $12/kg — baseline fuel cost assumption across 10-year TCO model

AUD $4.27M Total 10-Year TCO

Full 10-year projected TCO across capital, fuel, maintenance, and infrastructure

Green Hydrogen Production Strategy

Rather than relying on third-party hydrogen supply, the report proposed an on-site green hydrogen generation system as the more economically and strategically resilient option. The system was sized from first principles against KMC's fleet demand.

PEM electrolysis diagram showing cathode (2H+ + 2e- to H2), membrane, and anode (H2O to 2H+ + 1/2 O2 + 2e-) with flow field separator plates, GDL, and PTL components labelled
PEM electrolysis process — proton exchange membrane splits water to produce high-purity hydrogen and oxygen
Cummins HyLYZER 4000 containerized PEM electrolyzer unit — modular shipping-container-style system with visible tanks, piping, and electrical components
Cummins HyLYZER 4000 — containerized PEM electrolyzer selected for on-site green hydrogen production

Infrastructure CAPEX Breakdown

The total capital investment for the on-site green hydrogen generation system was modelled at AUD $2.66M — covering all major components from electrolyzer procurement through to workforce training and commissioning.

Expenditure Estimated Cost (AUD)
PEM Electrolyzer (100 kW — Cummins HyLYZER 4000) AUD $200,000
Solar PV System (640 kW array) AUD $768,000
Battery Energy Storage System (2 MWh LFP) AUD $1,400,000
RO Water Purification System AUD $40,000
Installation & Commissioning (10% of equipment) AUD $240,800
Workforce Training & Safety Certification AUD $15,000
Total CAPEX AUD $2,663,800

Government Incentives

Three Australian Government programs were identified as directly applicable to KMC's deployment scenario, collectively reducing the effective cost of adoption and de-risking the infrastructure investment:

Outcomes

Positive Feasibility Finding

Hydrogen fuel cell forklifts confirmed as technically and commercially viable for KMC's multi-shift, cold-storage, high-throughput logistics environment. Recommended over ICE and BEV alternatives.

10-Year TCO Quantified

AUD $4.27M total cost of ownership for a fleet of 10 over 10 years. Higher upfront capital offset by operational savings, zero fuel volatility, and zero carbon liability.

On-Site H₂ Production Sized

640 kW solar PV + Cummins HyLYZER 4000 + 2 MWh BESS system specified from first principles to produce 20,000 kg/year of green hydrogen at AUD $2.66M CAPEX.

Incentive Strategy Mapped

Three government programs identified (Hydrogen HeadStart, Industrial Hubs, R&D Tax Incentive) that materially improve the project's economics and reduce deployment risk.

Tools & Methods

TCO Modelling PEM Electrolysis Green Hydrogen Production Solar PV Sizing BESS Design Technology Benchmarking Lifecycle Cost Analysis Cummins HyLYZER 4000 Feasibility Assessment Government Incentive Mapping RO Water Treatment Emissions Analysis